ACCEPT IMPROVEMENTS AND FILE A NOTICE OF COMPLETION
FOR THE ANNUAL ROADWAY REHABILITATION AND SIDEWALK
REPAIR PROJECT The final construction cost for the Annual Roadway
Rehabilitation and Sidewalk Repair Project - Zone 6 is $2,640,126.68,
approximately 7% above the original contract amount of $2,464,122.
Additional quantities of various contract items were approved totaling
$63,028.68 and a contract change order in the amount of $112,976 was
requested by the City for additional work to repave the Citrus Ranch Park
parking lot. This project was funded through a combination of General
Fund, Measure M2 Fair Share, Gas Tax, Park Maintenance. The General
Fund was used to cover the cost of work performed on behalf of the City
of Irvine and the Irvine Ranch Water District. The City of Irvine will
reimburse $379,703 for work on Myford Road within their jurisdiction and
the Irvine Ranch Water District will reimburse $195,000 for adjustment of
their facilities to grade.
Recommendation: It is recommended that the City Council: 1. Adopt
Resolution No. 25-64 accepting the improvement of the Annual Roadway
Rehabilitation and Sidewalk Repair Project - Zone 6; and 2. Authorize the
City Engineer to execute and file the Notice of Completion with the
Orange County Recorder's Office. RESOLUTION NO. 25-64 A
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN,
CALIFORNIA, ACCEPTING THE PUBLIC WORKS AND IMPROVEMENT
AND AUTHORIZING THE RECORDATION OF THE NOTICE OF
COMPLETION FOR THE FISCAL YEAR 2024-25 ROADWAY
REHABILITATION AND SIDEWALK REPAIR PROJECT - ZONE 6, (CIP
NO. 70024) Fiscal Impact: The final construction cost for the Annual
Roadway Rehabilitation and Sidewalk Repair Project - Zone 6 is
$2,640,126.68, approximately 7% above the original contract amount of
$2,464,122. Additional quantities of various contract items were approved
totaling $63,028.68 and a contract change order in the amount of
$112,976 was requested by the City for additional work to repave the
Citrus Ranch Park parking lot. This project was funded through a
combination of General Fund, Measure M2 Fair Share, Gas Tax, Park
Maintenance. The General Fund was used to cover the cost of work
performed on behalf of the City of Irvine and the Irvine Ranch Water
District. The City of Irvine will reimburse $379,703 for work on Myford
Road within their jurisdiction and the Irvine Ranch Water District will
reimburse $195,000 for adjustment of their facilities to grade.