Tustin
City Council
5.
APPROVE SUPPLEMENTAL APPROPRIATION FOR THE EL CAMINO
REAL WATER MAIN RELOCATION PROJECT The City has partnered
with the Orange County Transportation Authority and Caltrans to complete
the El Camino Water Main Relocation Project which is necessary for
improvements to the I-5 and Red Hill Avenue exit ramp. Additional scope
of work has been requested by the partner agencies and staff have
negotiated a contract change order in the amount of $96,555.30 with G&A
Nelos Construction, Inc., which requires additional budget appropriation
and City Council approval. The full amount of all authorized change orders
will be reimbursed to the City by Orange County Transportation Authority.
Recommendation: It is recommended that the City Council: 1. Approve a
negotiated contract change order in the amount of $96,555.30 with G&A
Nelos Construction, Inc. and authorize the City Manager to execute the
contract change order on behalf of the City; and 2. Appropriate
$96,555.30 from Water Capital Fund. Fiscal Impact: On June 17, 2025,
the City Council awarded a construction contract to G&A Nelos
Construction, Inc. in the amount of $393,399.10 for the El Camino Water
Main Relocation Project. This action will approve a negotiated change
order and appropriate $96,555.30 from the Water Capital Fund to cover
the cost of additional work requested by the partner agencies. The
negotiated change order is eligible for reimbursement via Utility
Agreement COT-56, between the City of Tustin and the Orange County
Transportation Authority which authorizes the full reimbursement for final
design and all construction costs, minus an accrued depreciation credit of
$2,650.
AGENDA REPORT