AWARD CONSTRUCTION CONTRACT FOR THE EL CAMINO REAL
WATER MAIN RELOCATION PROJECT Staff is requesting the City
Council
award
a
construction
contract
to
the
lowest
responsive/responsible bidder for the El Camino Real Water Main
Relocation Project.
Recommendation: It is recommended that the City Council: 1. Award a
construction contract to the lowest responsive/responsible bidder, G&A
Nelos Construction, Inc. in the amount of $393,399.10 for the El Camino
Real Water Main Relocation Project and authorize the Mayor and the City
Clerk to execute the contract documents on behalf of the City; and 2.
Authorize the remaining project budgeted appropriation in excess of ten
percent (10%) above the contract amount as additional contingency.