Agenda Item
· Stanton
City Council — Item I
Original agenda text
Order of Business 9
9I.
ACCEPTANCE OF THE WESTERN STORM CHANNEL GRATE REPLACEMENT
PROJECT (TASK CODE NO. 2026-401) BY THE CITY COUNCIL OF THE CITY OF
STANTON, CALIFORNIA
The Western Storm Channel Replacement Project, consisting of the removal and
replacement of the storm channel inlet grate and all appurtenant work is now complete.
The final construction cost for the project was $28,395. The City Engineer, in his
judgment, certifies that the work was satisfactorily completed as of October 21, 2025, and
recommends that the City Council accept the completed work performed on this project.
RECOMMENDED ACTION:
1. City Council find that this project is exempt from the California Environmental Quality
Act (“CEQA”), Class 1, Section 15301(b) as minor alteration of existing public utility;
and
2. Accept the completion of improvements for the Western Storm Channel Grate
Replacement Project, as certified by the City Engineer, and affix the date of October
21, 2025, as the date of completion of all work on this project; and
3. Approve the final construction contract amount of $28,395 with G2 Construction, Inc.;
and
4. Direct the City Clerk within ten (10) days from the date of acceptance to file the Notice
of Completion (Attachment) with the County Clerk-Recorder of the County of Orange;
and
5. Direct City staff, after thirty-five (35) days has elapsed from the filing of the “Notice of
Completion” with the County Clerk-Recorder, to make the retention payment to G2
Construction, Inc. in the amount of $1,419.75.