ACCEPTANCE OF THE FY 2023/24 CITYWIDE ALLEY RESURFACING PROJECT
(TASK CODE NO. 2025-107) BY THE CITY COUNCIL OF THE CITY OF STANTON,
CALIFORNIA
The FY 2023/24 Citywide Alley Resurfacing Project consisting of demolition and
removals, clearing and grubbing, grading and earthwork, concrete work (ramps and
sidewalks), asphalt pavement, signing and striping, and all appurtenant work for various
alleys throughout the City of Stanton is now complete. The City Engineer, in his judgment,
certifies that the work was satisfactorily completed as of September 2, 2025, and
recommends that the City Council accept the completed work performed on this project.
Stanton City Council Agenda
RECOMMENDED ACTION:
1. City Council find that this project is exempt from the California Environmental Quality
Act (“CEQA”), Class 1, and 15301(c) as repair, maintenance, and minor alteration of
existing streets, sidewalks, gutters, and similar facilities; and
2. Accept the completion of improvements for the FY 2023/24 Citywide Alley Resurfacing
Project, as certified by the City Engineer, and affix the date of September 9, 2025, as
the date of completion of all work on this project; and
3. Approve the final construction contract amount of $661,250.00 with Sequel
Contractors, Inc.; and
4. Direct the City Clerk within ten (10) days from the date of acceptance to file the Notice
of Completion (Attachment) with the County Clerk-Recorder of the County of Orange;
and
5. Direct City staff, after thirty-five (35) days has elapsed from the filing of the “Notice of
Completion” with the County Clerk-Recorder, to make the retention payment to Sequel
Contractors, Inc. in the amount of $33,062.50.