ACCEPTANCE OF THE FISCAL YEAR (FY) 2024/2025 SEWER REHABILIATION
PROJECT (TASK CODE NO. 2025-301) BY THE CITY COUNCIL OF THE CITY OF
STANTON, CALIFORNIA
The FY 2024/2025 Sewer Rehabilitation Project consisting of cleaning the sewer lines,
traffic control, installing Cured-in-Place Pipe (CIPP) Liner, manhole repairs and
adjustments, post CCTV inspection and all appurtenant work is now complete. The final
construction cost for the project was $233,725.00. The City Engineer, in his judgment,
certifies that the work was satisfactorily completed as of September 9, 2025, and
recommends that the City Council accept the completed work performed on this project.
RECOMMENDED ACTION:
1. City Council find that this project is exempt from the California Environmental Quality
Act (“CEQA”), Class 1, Section 15301(b) as maintenance, repair, and minor alteration
of existing publicly owned sewerage utilities; and
2. Accept the completion of improvements for the FY 2024/2025 Sewer Rehabilitation
Project, as certified by the City Engineer, and affix the date of September 9, 2025, as
the date of completion of all work on this project; and
3. Approve the final construction contract amount of $233,725.00 with Tunnelworks
Services, Inc.; and
4. Direct the City Clerk within ten (10) days from the date of acceptance to file the Notice
of Completion with the County Clerk-Recorder of the County of Orange; and
5. Direct City staff, after thirty-five (35) days has elapsed from the filing of the “Notice of
Completion” with the County Clerk-Recorder, to make the retention payment to