Agenda Item
· Bell Gardens
City Council — Item 13
Original agenda text
Order of Business 10
10.13 Acceptance of the Various Residential Streets Project (CIP No.
3940) as Complete
RECOMMENDATION: It is staff’s recommendation that the City
Council:
1. Accept the construction contract for the Various Residential
Street Improvements, FY 2024/2025 (CIP No. 3940) as
complete, and
2. Authorize staff to file the Notice of Completion.
CONCLUSION: The City Council’s acceptance of the Project as
complete is required to allow the City Clerk to file the Notice of
Completion with the LA County Registrar-Recorder.
FISCAL IMPACT: The City's FY25/26 capital improvement project
budget allocated $1,245,168 in Measure R and Measure M funds.
Furthermore, the City Council approved an additional appropriation
of $200,000 in Measure M funds, $303,000 in Measure R funds, and
$250,000 in Prop C funds to cover all construction and project
management costs, including contingency. The total Project budget
was $1,998,168, and the final Project cost was $1,817,656.90,
including design, construction management, project management
and construction. The Project was completed within budget. The
unused balances will be returned to their respective funds.
Project budget:
Measure R
$ 975,735.00
Measure M
$ 772,433.00
Prop C Local Return
$ 250,000.00
TOTAL BUDGET
$ 1,998,168.00
Project costs:
Design
$ 89,313.00
Geotechnical and Topographic Survey
$ 15,997.00
Project Management
$ 57,819.00
Construction Management and Inspections
$ 82,631.00
Funding Administration
$ 21,682.00
Publication & Misc.
$ 1,305.00
Actual Construction Cost - Base Bid
$ 1,029,672.34
Actual Construction Cost - Additive Bid A
$ 519,237.56
Contingency
$ -
TOTAL PROJECT COST
$ 1,817,656.90
ATTACHMENTS:
Exhibit 1 - Notice of Completion