Agenda Item · Bell Gardens

City Council — Item 9

Bell Gardens October 13, 2025 City Council Item 9
Original agenda text Order of Business 10
10.9 Acceptance of the Purchase and Installation of Solar-Powered Lighting at Darwell Park as Complete RECOMMENDATION: It is staff’s recommendation that the City Council: 1. Accept the Purchase and Installation of Solar-Powered Lighting at Darwell Park as complete; and 2. Authorize staff to file the Notice of Completion. CONCLUSION: The City Council’s acceptance of the Project as complete is required to allow the City Clerk to file the Notice of Completion with the LA County Registrar-Recorder. Upon approval of the City Council, staff will file the Notice of Completion. FISCAL IMPACT: The total Project cost of $20,608.45 was funded with general funds. ATTACHMENTS: Exhibit 1 - Notice of Completion