Agenda Item
· Bell Gardens
City Council — Item 8
Original agenda text
Order of Business 10
10.8
Consideration of Acceptance of the Soil Remediation Project
at the Former Berk Oil Site (CIP No. 3927)
RECOMMENDATION:
It is staff’s recommendation that the City Council:
1. Accept the Construction Contract of Resource Environmental,
Inc. for the Soil Remediation Project at Former Berk Oil Site as
Complete; and
2. Appropriate an additional $65,678.20 in ECRG funds to cover
costs that exceeded the original construction contract and
contingency; and
3. Authorize staff to file the Notice of Completion.
CONCLUSION: The City Council’s acceptance of the Project as
complete is required to allow the City Clerk to file the Notice of
Completion with the LA County Registrar-Recorder.
FISCAL IMPACT: The Project performed was funded through the
Equitable Community Revitalization Grant (ECRG) program received
from Department of Toxic Substances Control (DTSC). The final
Project construction cost including change orders is $2,583,578.64.
The construction budget was $2,517,900.44, including contingency.
Therefore, an additional appropriation of $65,678.20 is necessary to
cover the total construction costs after Change Orders.
The table below illustrates the total construction cost and
construction budget:
Actual Construction Cost – Base Bid
$
2,179,988.26
Change Orders No.1 - 4
$
403,590.38
Total Project Costs
$
2,583,578.64
Original Contract
contingency
Amount,
including
Total Project Costs
10% $ 2,517,900.44
$ 2,583,578.64
Additional Funding Required due to Change $
Orders
65,678.20
ATTACHMENTS:
Exhibit 1 - Notice of Completion