9. NOTICE OF COMPLETION: WATER MAIN REPLACEMENT PROJECT ON CONCORD
AVENUE AND MIDVALE PLACE - F2M24-68, C2M25-8, M2M26-50
On March 24, 2025, the City Council awarded a contract to Stephen Doreck Equipment
Rentals Inc. for the Water Main Replacement Project on Concord Avenue and Midvale
Place in the amount of $1,552,135.00. There was one authorized change order during the
project to install one 2-inch water service line, additional concrete work, and also included
various miscellaneous items credited to City. The change order decreased the total
amount of the contract by $44,887.74. The project has been completed in accordance with
the City’s requirements and specifications. As such, it would be appropriate for the City
Council to accept the project as complete and instruct the City Clerk that the Notice of
Completion be filed with the County of Los Angeles Recorder’s Office.
Recommended Action: City Council accept the work of Stephen Doreck Equipment
Rentals Inc., for the Water Main Replacement Project on Concord Avenue and Midvale
Place as complete in the amount of $1,507,247.26; direct the City Clerk to file a Notice of
Completion with the County of Los Angeles for recordation; instruct the Finance Director
to release the five percent retention 35 days from the date of recordation if no liens are
filed; and, direct staff to undertake the steps necessary to finalize Council’s action.