9. APPROVAL OF A CHANGE ORDER TO CONTRACT FOR THE STORM DRAIN
REHABILITATION PROJECT ON CARLOS AVENUE - F2M25-64, C2M26-5, M2M26-
On January 26, 2025, the City Council approved an award of Contract to Torres Sanitation
Systems Construction for the Storm Drain Rehabilitation Project on Carlos Avenue in an
amount not to exceed $100,300.00 (C2M26-5). The Storm Drain Pipe Repair Project
originally intended to rehabilitate a failing drainage line from 2027 Carlos Avenue to
Montezuma Avenue. Due to the alignment passing multiple private properties, a
trenchless pipe-lining method was selected to minimize surface disruption. However, pre-
lining video inspections revealed severe structural deterioration undetected during initial
assessments. Portions of the existing corrugated metal pipe were completely rusted out,
leaving the pipe without a bottom section. This structural failure made immediate
trenchless lining technically infeasible without structural stabilization. To resolve this issue
and complete the project, the contractor must perform open-trench spot repairs at three
distinct locations. This proposed Change Order covers the direct costs of these structural
spot repairs, alongside necessary site restoration efforts including concrete paving, soil
leveling, and property cleaning.
Recommended Action: City Council approve Change Order No. 1 for the Storm
Drain Rehabilitation Project on Carlos Avenue, increasing Contract No. C2M26-5 with
Torres Sanitation Systems Construction by $48,000.00 and bringing the total revised
contract value to an amount not to exceed $148,300.00 to complete the project;
appropriate $48,000.00 from the Safe Clean Water Program Fund to cover the change
order; and, direct staff to undertake the steps necessary to finalize the Council’s action.
(M2M26-83)