Agenda Item
· Stanton
City Council — Item G
Original agenda text
Order of Business 9
9G. ACCEPTANCE OF THE STANFORD AVENUE STORM DRAIN REPAIR PROJECT BY
THE CITY COUNCIL OF THE CITY OF STANTON, CALIFORNIA
The Stanford Avenue Storm Drain Repair Project consisting of cleaning the storm drain
lines, traffic control, installing Cured-in-Place Pipe (CIPP) Liner, post-closed-circuit
television (CCTV) inspection and all appurtenant work for the storm drains located at
Beach Boulevard and Stanford Avenue is now complete. The final construction cost for
the project was $47,867.50, which is below the project budget amount. The City Engineer,
in his judgment, certifies that the work was satisfactorily completed as of February 22,
2024 and recommends that the City Council accept the completed work performed on
this project.
RECOMMENDED ACTION:
1. City Council declare this project categorically exempt under the California
Environmental Quality Act, Class 1, and 15301(c) as repair, maintenance, and minor
alteration of existing public structures; and
2. Accept the completion of improvements for the Stanford Avenue Storm Drain Repair
Project, as certified by the City Engineer, and affix the date of February 22, 2024 as
the date of completion of all work on this project; and
3. Approve the final construction contract amount of $47,867.50 with Tunnelworks
Services, Inc.; and
4. Direct the City Clerk within ten (10) days from the date of acceptance to file the Notice
of Completion (Attachment) with the County Clerk-Recorder of the County of Orange;
and
5. Direct City staff, after thirty-five (35) days has elapsed from the filing of the “Notice of
Completion” with the County Clerk-Recorder, to make the retention payment to
Tunnelworks Services, Inc. in the amount of $2,393.38.
March 12, 2024