13. NOTICE OF COMPLETION: INTERIOR COATINGS OF TREATMENT VESSELS 204 A
AND 204 B AT THE GROUND WATER TREATMENT PLANT – F2M24-47,
C2M24-48, M2M25-68
On July 22,2024, the City Council awarded a contract to Unified Field Services Corp. for
the Interior Coatings of Water Treatment Vessels 204 A and 204 B at the Ground Water
Treatment Plant in the amount of $110,600.00. There was one authorized change order
during the project. The change order was to provide an engineer to inspect internal
corrosion and recommendations for the two vessels. The change order increased the total
amount of the contract by $10,350.00, for a total project cost of $120,950.00. The project
has been completed in accordance with the City’s requirements and specifications. As
such, it would be appropriate for the City Council to accept the project as complete and
instruct the City Clerk that the Notice of Completion be filed with the County of Los Angeles
Recorder’s Office.
Recommended Action: City Council accept the work of Unified Field Services Corp.
for the Interior Coatings of Water Treatment Vessels 204 A and 204 B at the Ground Water
Treatment Plant as complete in the amount of $120,950.00; direct the City Clerk to file a
Notice of Completion with the County of Los Angeles for recordation; direct the Finance
Director to release the five percent retention 35 days from the date of recordation if no
liens are filed; and, direct staff to undertake the steps necessary to finalize Council’s
action. (M2M25-68)