APPROVAL OF CHANGE ORDER: FY 2022-2023 SB1 STREET REHABILITATION
PROJECT – F2M22-39, C2M24-62, M2M25-140
On October 14, 2024, the City Council awarded a contract to DASH Construction
Company, Inc. for the FY 2022-23 SB1 Street Rehabilitation Project in the amount of
$2,042,913.00 (C2M24-62). Change Order Nos. 1 and 2 were previously issued for
replacement of traffic loops and alley reconstruction at 1920 W. Hellman Ave. in the total
amount of $ 132,232.50. Additional work is now necessary for more cross gutters for
proper street drainage, curb & gutter and concrete driveway aprons. Further, additional
pavement rehabilitation is needed to accommodate unforeseen field conditions within the
project limits. This additional work under Change Order No. 3 requires another
$358,240.70 in expenses, resulting in a revised contract value of $2,533,385.70.
Recommended Action:
City Council approve Change Order No. 3 for the FY 202223 SB1 Street Rehabilitation Project, increasing Contract No. C2M24-62 with DASH
Construction Company, Inc. by $358,240.70, bringing the total revised contract value to
$2,533,385.70, subject to approval by the City Manager and City Attorney, direct the
Finance Director to appropriate $358,240.70 from the SB1 Road Maintenance and
Rehabilitation Fund; and, direct staff to undertake the steps necessary to finalize Council’s
action. (M2M25-140)