9D. ACCEPTANCE OF THE CONSTRUCTION OF THE STANTON PARK FITNESS
EQUIPMENT PROJECT BY THE CITY COUNCIL OF THE CITY OF STANTON,
CALIFORNIA
The Stanton Park Fitness Equipment Project consists of demolition, concrete work (slab
and walkway access), installation of fitness equipment, and all appurtenant work is now
complete. The City Engineer, in his judgement, certifies that the work was substantially
completed as of April 11, 2024 and recommends that the City Council accept the complete
work performed on this project.
RECOMMENDED ACTION:
1. City Council declare this project categorically exempt under the California
Environmental Quality Act, Class 1, and 15301(c) as repair, maintenance, and minor
alteration of existing public structures; and
2. Accept the completion of improvements for the Stanton Park Fitness Equipment
Project, as certified by the City Engineer, and affix the date of April 11, 2024 as the
substantial date of completion for all work on this project; and
3. Approve the final construction contract amount of $42,000 with Aguilar & Calderon, a
corporation; and
4. Direct the City Clerk within ten (10) days from the date of acceptance to file the Notice
of Completion (Attachment) with the County Clerk-Recorder of the County of Orange;
and
5. Direct City staff, after thirty-five (35) days has elapsed from the filing of the “Notice of
Completion” with the County Clerk-Recorder, to make the retention payment to Aguilar
& Calderon, a corporation, in the amount of $2,100.00.
April 23, 2024