14. Award of Bid – Walnut Ranch Park Storm Drain Improvement Project
Recommendation: That the City Council:
1. Award a construction contract for the Walnut Ranch Park Storm Drain
Improvement Project to Perry C. Thomas, Inc. in the amount of
$186,241.00;
2. Reject all other bids;
3. Appropriate $274,865.00 from American Rescue Plan Act (ARPA) Fund
Reserves to the Walnut Ranch Storm Drain Improvement Project;
4. Authorize staff to issue a Purchase Order to Perry C. Thomas, Inc. in the
amount of $186,241.00;
5. Authorize staff to issue change orders not to exceed 10% of the contract
award amount ($18,624.10) to Perry C. Thomas, Inc.; and
6. Approve a Purchase Order to RKA Consulting Group in the amount of
$58,390.