10. NOTICE OF COMPLETION: POLICE DEPARTMENT BUILDING ROOFING PROJECT
– F2M23-43, C2M23-51, M2M23-203
On June 26, 2023, the City Council awarded a contract to Wiltshire Urethane Foam
Company for the Police Department Building Roofing Project in the amount of
$320,400.00. There was one change order in the amount of $20,500.00 to cover an
additional 100 square feet of roof. The existing rock roof was removed over the Motor’s
garage, and it was replaced with the current treatment. This project has been inspected
by staff and all work has been completed in accordance with the City’s requirements and
specifications. As such, it would be appropriate for the City Council to accept this project
as complete and instruct that the Notice of Completion be filed with the County of Los
Angeles Recorder’s Office.
Recommended Action: City Council accept the work of Wiltshire Urethane Foam
Company for the repair and application of polyurethane foam sealer to the Police
Department building roof as complete in the amount of $340,900.00; direct the City Clerk
to file a Notice of Completion with the County of Los Angeles for recordation; instruct the
Finance Director to release the 5% retention 35 days from the date of recordation if no
liens are filed; and, direct staff to undertake the steps necessary to finalize Council’s